Substrate preparation
Remove loose or weak concrete, oil, dust and contamination. Mechanically roughen unsuitable smooth areas.
Give contractors and project buyers the information required to evaluate, test and apply the material responsibly.

Remove loose or weak concrete, oil, dust and contamination. Mechanically roughen unsuitable smooth areas.
Pre-wet the substrate thoroughly and remove standing water before placement.
Use clean water at 16%–18% of product weight and mechanically mix for approximately 3 minutes.
Complete final placement within approximately 10 minutes after mixing under standard conditions.
Apply only when air and substrate temperatures are between 5°C and 35°C.
Protect the repair from premature traffic, rain, strong wind, extreme heat and freezing.